ITAC Assessment: IA0165
ITAC logo
ITAC Assessment: IA0165
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product conveyor pulleys
NAICS
n/a
SIC 3565: Packaging Machinery
Sales Range $10
M
to 50
M
# of Employees 240
Plant Area 92,900
ft2
Annual Production 8,600,000
lb
Production Hrs. Annual 6,056
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $50,809 2,287,222
kWh
Electricity Demand $18,282 5,448
kW-mo/yr
Natural Gas $25,837 5,753
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $54,041 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $40,215

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 3.1192: Reduce scrap production $22,752 $48 - - $432
-
lb
- - $22,320 -
02 4.652: Replace existing equipment with more suitable substitutes $12,823 $3,500 - - - $12,823 - - -
03 2.8113: Purchase gas directly from a contract gas supplier $9,895 $4,200 - - - - $9,895 - -
04 3.2121: Convert to electrostatic powder coating $3,771 $2,598 - - - - - $3,562 $209
05 2.4231: Reduce the pressure of compressed air to the minimum required $1,788 $12 $964
48,359
kWh
$824
-
kW-mo/yr
- - - - -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,421 $167 $762
38,394
kWh
$659
-
kW-mo/yr
- - - - -
07 3.1191: Change procedures / equipment / operating conditions $1,431 $1,500 - - - $82 - - $1,349
08 4.652: Replace existing equipment with more suitable substitutes $160 - - - - $160 - - -
TOTAL RECOMMENDED $54,041 $12,025 $1,726
86,753
kWh
$1,483
-
kW-mo/yr
$432
-
lb
$13,065 $9,895 $25,882 $1,558
TOTAL IMPLEMENTED $40,215 $5,227 $1,726
86,753
kWh
$1,483
-
kW-mo/yr
$432
-
lb
$12,905 - $22,320 $1,349
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs