Assessment Year | 1996 |
---|---|
Principal Product | corn chips |
NAICS |
n/a
|
SIC | 2096: Potato Chips, Corn Chips, and Similar Snacks |
Sales Range | $10 M to 50M |
# of Employees | 75 |
Plant Area |
40,146
ft2
|
Annual Production | 19,500,000
lb
|
Production Hrs. Annual | 6,864
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $43,241 | 2,074,443 |
kWh
|
$0.021 |
Electricity Demand | $23,063 | 3,876 |
kW-mo/yr
|
$5.95 |
Natural Gas | $178,168 | 71,904 |
MMBtu
|
$2.48 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $6,110 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,235 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1213: Direct warmest air to combustion intake | $1,085 | $1,030 | - | - |
$1,085
-
MMBtu
|
- | |
02 | 2.1213: Direct warmest air to combustion intake | $1,072 | $280 | - | - |
$1,072
-
MMBtu
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $836 | $1,852 |
$308
27,550
kWh
|
$528
-
kW-mo/yr
|
- | - | |
04 | 2.7135: Install occupancy sensors | $627 | $693 |
$231
20,516
kWh
|
$396
-
kW-mo/yr
|
- | - | |
05 | 2.4239: Eliminate or reduce compressed air usage | $1,525 | $250 |
$561
50,117
kWh
|
$964
-
kW-mo/yr
|
- | - | |
06 | 3.3128: Utilize other methods to remove contaminants | $450 | $750 | - | - | - | $450 | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $442 | $25 |
$152
13,482
kWh
|
$290
-
kW-mo/yr
|
- | - | |
08 | 2.4133: Use most efficient type of electric motors | $73 | $94 |
$28
2,345
kWh
|
$45
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $6,110 | $4,974 |
$1,280
114,010
kWh
|
$2,223
-
kW-mo/yr
|
$2,157
-
MMBtu
|
$450 | ||
TOTAL IMPLEMENTED | $2,235 | $2,567 |
$259
22,861
kWh
|
$441
-
kW-mo/yr
|
$1,085
-
MMBtu
|
$450 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs