ITAC Assessment: IA0153
ITAC logo
ITAC Assessment: IA0153
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product dairy products
NAICS
n/a
SIC 2026: Fluid Milk
Sales Range $1
M
to 5
M
# of Employees 40
Plant Area 65,000
ft2
Annual Production 65,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $74,939 3,310,668
kWh
Electricity Demand $81,648 6,864
kW-mo/yr
Electricity Fees $10,077 -
Natural Gas $88,540 22,023
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $31,419 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,478

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings
01 3.4111: Use closed cycle process to minimize waste water production $8,102 $2,678 - - - - $8,102
-
Tgal
02 2.2425: Use flue gases to heat process or service water $5,206 $22,090 - - - $5,206
-
MMBtu
-
03 2.4133: Use most efficient type of electric motors $1,805 $4,646 $1,150
57,444
kWh
$655
-
kW-mo/yr
- - -
04 2.1233: Analyze flue gas for proper air/fuel ratio $3,758 $2,000 - - - $3,758
-
MMBtu
-
05 3.4111: Use closed cycle process to minimize waste water production $3,111 $354 - - - - $3,111
-
Tgal
06 2.7142: Utilize higher efficiency lamps and/or ballasts $2,949 $4,617 $1,870
93,494
kWh
$1,079
-
kW-mo/yr
- - -
07 4.811: Demolish old building to reduce tax and insurance bills $2,570 $250 - - $2,570 - -
08 2.2628: Utilize a less expensive cooling method $1,124 $4,500 $842
36,635
kWh
$282
-
kW-mo/yr
- - -
09 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,892 $2,167 $1,198
59,789
kWh
$694
-
kW-mo/yr
- - -
10 2.1213: Direct warmest air to combustion intake $659 $659 - - - $659
-
MMBtu
-
11 3.4154: Eliminate leaks in water lines and valves $243 $250 - - - - $243
-
Tgal
TOTAL RECOMMENDED $31,419 $44,211 $5,060
247,362
kWh
$2,710
-
kW-mo/yr
$2,570 $9,623
-
MMBtu
$11,456
-
Tgal
TOTAL IMPLEMENTED $16,478 $9,824 $1,150
57,444
kWh
$655
-
kW-mo/yr
$2,570 $3,758
-
MMBtu
$8,345
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs