Assessment Year | 1995 |
---|---|
Principal Product | lead acid batteries |
NAICS |
n/a
|
SIC | 3692: Primary Batteries, Dry and Wet |
Sales Range | $10 M to 50M |
# of Employees | 89 |
Plant Area |
67,000
ft2
|
Annual Production | 500,000
pieces
|
Production Hrs. Annual | 5,880
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $198,651 | 6,100,235 |
kWh
|
$0.033 |
Natural Gas | $26,308 | 5,437 |
MMBtu
|
$4.84 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $22,743 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,857 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,141 | $1,000 |
$2,141
65,944
kWh
|
- | - | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,014 | $684 |
$1,014
31,067
kWh
|
- | - | |
03 | 2.4237: Substitute compressed air cooling with water or air cooling | $111 | $193 |
$111
3,517
kWh
|
- | - | |
04 | 2.7124: Make a practice of turning off lights when not needed | $1,348 | - |
$1,348
41,325
kWh
|
- | - | |
05 | 2.7135: Install occupancy sensors | $806 | $1,370 |
$806
24,912
kWh
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,078 | $13,034 |
$3,078
94,666
kWh
|
- | - | |
07 | 3.1191: Change procedures / equipment / operating conditions | $8,243 | $75 | - | - |
$8,243
-
lb
|
|
08 | 3.6112: Use filter and drying oven to reduce sludge volume | $3,818 | $5,467 | - | - |
$3,818
-
lb
|
|
09 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $2,184 | $3,600 | - |
$2,184
-
lb
|
- | |
TOTAL RECOMMENDED | $22,743 | $25,423 |
$8,498
261,431
kWh
|
$2,184
-
lb
|
$12,061
-
lb
|
||
TOTAL IMPLEMENTED | $10,857 | $21,555 |
$7,039
216,589
kWh
|
- |
$3,818
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs