Assessment Year | 1994 |
---|---|
Principal Product | molded plastic parts |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 220 |
Plant Area |
103,244
ft2
|
Annual Production | 16,000,000
lb
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $295,689 | 7,235,932 |
kWh
|
$0.041 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $18,118 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,666 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $8,897 | $18,400 |
$8,897
217,761
kWh
|
- | |
02 | 2.2437: Recover waste heat from equipment | $2,317 | $730 | - |
$2,317
-
MMBtu
|
|
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $467 | - |
$467
11,430
kWh
|
- | |
04 | 2.4221: Install compressor air intakes in coolest locations | $456 | $150 |
$456
11,137
kWh
|
- | |
05 | 2.7235: Install fossil fuel make-up air unit | $1,745 | $9,000 | - |
$1,745
-
MMBtu
|
|
06 | 2.7135: Install occupancy sensors | $1,319 | $855 |
$1,319
32,239
kWh
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,254 | $862 |
$1,254
30,774
kWh
|
- | |
08 | 2.7111: Reduce illumination to minimum necessary levels | $212 | $70 |
$212
5,275
kWh
|
- | |
09 | 2.3212: Optimize plant power factor | $1,451 | $4,140 |
$1,451
-
kWh
|
- | |
TOTAL RECOMMENDED | $18,118 | $34,207 |
$14,056
308,616
kWh
|
$4,062
-
MMBtu
|
||
TOTAL IMPLEMENTED | $14,666 | $33,257 |
$12,921
280,774
kWh
|
$1,745
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs