ITAC Assessment: IA0053
ITAC logo
ITAC Assessment: IA0053
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product batteries
NAICS
n/a
SIC 3692: Primary Batteries, Dry and Wet
Sales Range $10
M
to 50
M
# of Employees 320
Plant Area 193,475
ft2
Annual Production 241,000,000
pieces
Production Hrs. Annual 4,288
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $467,736 11,917,937
kWh
Natural Gas $146,192 112,422
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $12,223 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,636

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7314: Reduce ventilation air $1,768 $5,000 - $1,768
-
MMBtu
02 2.7135: Install occupancy sensors $6,868 $4,490 $6,868
174,971
kWh
-
03 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air $3,542 $10,000 $3,515
89,683
kWh
$27
-
MMBtu
04 2.1213: Direct warmest air to combustion intake $45 $184 - $45
-
MMBtu
TOTAL RECOMMENDED $12,223 $19,674 $10,383
264,654
kWh
$1,840
-
MMBtu
TOTAL IMPLEMENTED $8,636 $9,490 $6,868
174,971
kWh
$1,768
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs