Assessment Year | 2006 |
---|---|
Principal Product | Beef cows slaughtered |
NAICS | 311612: Meat Processed from Carcasses |
SIC | 2011: Meat Packing Plants |
Sales Range | $100 M to 500M |
# of Employees | 300 |
Plant Area |
55,000
ft2
|
Annual Production | 170,000
pieces
|
Production Hrs. Annual | 7,344
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $516,233 | 12,785,600 |
kWh
|
$0.040 |
Electricity Demand | $209,682 | 28,992 |
kW-mo/yr
|
$7.23 |
Electricity Fees | $42,354 | - |
|
- |
Natural Gas | $939,206 | 108,221 |
MMBtu
|
$8.68 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $172,627 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $143,011 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.8112: Combine utility meters | $71,000 | $100,000 | - | - | $71,000 | - | - | - | - | |
02 | 4.132: Purchase new equipment to reduce material use / cost | $37,900 | $600 | - | - | - | - | - | $37,900 | - | |
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $22,000 | $51,000 | - | - | - |
$22,000
-
MMBtu
|
- | - | - | |
04 | 2.2511: Insulate bare equipment | $13,750 | $2,100 | - | - | - |
$13,750
-
MMBtu
|
- | - | - | |
05 | 3.8221: Use alternatives for acids / alkaline (water, steam, abrasive) | $7,616 | $25,000 | - | - | - | - | - | - | $7,616 | |
06 | 2.2136: Install / repair insulation on steam lines | $9,000 | $500 | - | - | - |
$9,000
-
MMBtu
|
- | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,240 | $400 |
$2,500
55,100
kWh
|
$740
-
kW-mo/yr
|
- | - | - | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,900 | $9,900 |
$2,200
48,400
kWh
|
$700
-
kW-mo/yr
|
- | - | - | - | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,430 | $1,620 |
$1,900
42,040
kWh
|
$530
-
kW-mo/yr
|
- | - | - | - | - | |
10 | 2.4314: Use synthetic lubricant | $733 | - |
$565
12,450
kWh
|
$168
-
kW-mo/yr
|
- | - | - | - | - | |
11 | 2.7134: Use photocell controls | $1,120 | $100 |
$700
15,350
kWh
|
$420
-
kW-mo/yr
|
- | - | - | - | - | |
12 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $938 | $215 |
$360
8,065
kWh
|
$160
-
kW-mo/yr
|
- | - | $418 | - | - | |
TOTAL RECOMMENDED | $172,627 | $191,435 |
$8,225
181,405
kWh
|
$2,718
-
kW-mo/yr
|
$71,000 |
$44,750
-
MMBtu
|
$418 | $37,900 | $7,616 | ||
TOTAL IMPLEMENTED | $143,011 | $115,435 |
$8,225
181,405
kWh
|
$2,718
-
kW-mo/yr
|
$71,000 |
$22,750
-
MMBtu
|
$418 | $37,900 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs