| Assessment Year | 2000 |
|---|---|
| Principal Product | Textile Machinery |
| NAICS |
n/a
|
| SIC | 3552: Textile Machinery |
| Sales Range | $1 M to 5M |
| # of Employees | 50 |
| Plant Area |
66,000
ft2
|
| Annual Production | 4,500
pieces
|
| Production Hrs. Annual | 4,680
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $41,513 | 799,238 |
kWh
|
$0.052 |
| Electricity Demand | $32,462 | 3,269 |
kW-mo/yr
|
$9.93 |
| Electricity Fees | $1,417 | - |
|
- |
| Natural Gas | $26,740 | 3,043 |
MMBtu
|
$8.79 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $33,270 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $8,109 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,372 | $18,408 |
$5,619
108,148
kWh
|
$2,753
-
kW-mo/yr
|
- | - | |
| 02 | 2.7124: Make a practice of turning off lights when not needed | $1,241 | $106 |
$836
16,120
kWh
|
$405
-
kW-mo/yr
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $907 | $2,794 |
$609
11,723
kWh
|
$298
-
kW-mo/yr
|
- | - | |
| 04 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $588 | - |
$588
11,430
kWh
|
- | - | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,364 | $600 |
$3,364
64,771
kWh
|
- | - | - | |
| 06 | 2.6218: Turn off equipment when not in use | $1,013 | - |
$1,013
19,637
kWh
|
- | - | - | |
| 07 | 4.611: Begin a practice of predictive / preventative maintenance | $2,970 | $396 | - | - | - | $2,970 | |
| 08 | 2.8113: Purchase gas directly from a contract gas supplier | $2,674 | $500 | - | - | - | $2,674 | |
| 09 | 4.632: Change operating conditions | $7,539 | $1,000 | - | - | - | $7,539 | |
| 10 | 2.8114: Change rate schedules or other changes in utility service | $4,068 | $20,000 | - | - | - | $4,068 | |
| 11 | 4.322: Eliminate old stock and modify inventory control | $534 | $515 | - | - |
$534
-
lb
|
- | |
| TOTAL RECOMMENDED | $33,270 | $44,319 |
$12,029
231,829
kWh
|
$3,456
-
kW-mo/yr
|
$534
-
lb
|
$17,251 | ||
| TOTAL IMPLEMENTED | $8,109 | $1,617 |
$4,200
80,891
kWh
|
$405
-
kW-mo/yr
|
$534
-
lb
|
$2,970 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs