ITAC Assessment: BD0259
ITAC logo
ITAC Assessment: BD0259
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Margarine
NAICS 311512: Creamery Butter Manufacturing
SIC 2021: Creamery Butter
Sales Range $10
M
to 50
M
# of Employees 110
Plant Area 40,000
ft2
Annual Production 153,764,535
lb
Production Hrs. Annual 6,240
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $546,213 9,338,246
kWh
Electricity Demand $94,633 23,165
kW-mo/yr
Natural Gas $190,663 32,393
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $90,792 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $84,292

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
01 2.6218: Turn off equipment when not in use $31,009 - $27,334
467,251
kWh
$3,675
-
kW-mo/yr
- - - -
02 2.4133: Use most efficient type of electric motors $11,519 $12,700 $10,460
178,956
kWh
$1,059
-
kW-mo/yr
- - - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $5,350 $6,635 $4,650
79,497
kWh
$700
-
kW-mo/yr
- - - -
04 2.1213: Direct warmest air to combustion intake $5,339 $2,000 $(-243.0)
(-4,160)
kWh
$(-25.0)
-
kW-mo/yr
$5,607
-
MMBtu
- - -
05 2.7135: Install occupancy sensors $4,522 $2,700 $3,631
62,076
kWh
$891
-
kW-mo/yr
- - - -
06 2.4221: Install compressor air intakes in coolest locations $4,493 $1,500 $3,911
66,858
kWh
$582
-
kW-mo/yr
- - - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $4,373 $9,540 $4,254
72,758
kWh
$572
-
kW-mo/yr
- $49 $(-502.0) -
08 2.4231: Reduce the pressure of compressed air to the minimum required $4,141 - $3,605
61,628
kWh
$536
-
kW-mo/yr
- - - -
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,968 $400 $1,796
30,688
kWh
$172
-
kW-mo/yr
- - - -
10 2.1222: Install turbulators $1,916 $1,200 - - $1,916
-
MMBtu
- - -
11 2.7134: Use photocell controls $228 $300 $160
2,741
kWh
$38
-
kW-mo/yr
- $15 $15 -
12 2.7142: Utilize higher efficiency lamps and/or ballasts $211 $150 $117
1,997
kWh
$11
-
kW-mo/yr
- $35 $48 -
13 4.642: Install sensors to detect and avoid jams $15,723 $3,000 - - - - - $15,723
TOTAL RECOMMENDED $90,792 $40,125 $59,675
1,020,290
kWh
$8,211
-
kW-mo/yr
$7,523
-
MMBtu
$99 $(-439.0) $15,723
TOTAL IMPLEMENTED $84,292 $29,235 $55,304
945,535
kWh
$7,628
-
kW-mo/yr
$5,607
-
MMBtu
$15 $15 $15,723
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs