| Assessment Year | 1999 |
|---|---|
| Principal Product | Power Supplies |
| NAICS |
n/a
|
| SIC | 3612: Power, Distribution, and Specialty Transformers |
| Sales Range | $10 M to 50M |
| # of Employees | 275 |
| Plant Area |
36,000
ft2
|
| Annual Production | 20,000
pieces
|
| Production Hrs. Annual | 2,375
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $51,956 | 924,971 |
kWh
|
$0.056 |
| Electricity Demand | $97,239 | 4,278 |
kW-mo/yr
|
$22.73 |
| Electricity Fees | $6,213 | - |
|
- |
| Natural Gas | $26,246 | 3,147 |
MMBtu
|
$8.34 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $20,698 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $931 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7111: Reduce illumination to minimum necessary levels | $931 | - |
$931
16,706
kWh
|
- | - | - | - | |
| 02 | 2.6242: Minimize operation of equipment maintained in standby condition | $400 | - |
$400
7,034
kWh
|
- | - | - | - | |
| 03 | 2.7229: Air condition only space necessary | $2,807 | $5,000 |
$925
16,413
kWh
|
$1,882
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $2,786 | $2,500 |
$2,420
82,063
kWh
|
$366
-
kW-mo/yr
|
- | - | - | |
| 05 | 4.321: Optimize production lot sizes and inventories | $3,750 | $5,000 | - | - | - | - | $3,750 | |
| 06 | 4.111: Add equipment/ operators to reduce production bottleneck | $2,813 | $360 | - | - | - | - | $2,813 | |
| 07 | 4.632: Change operating conditions | $899 | $1,040 | - | - | - | - | $899 | |
| 08 | 3.4151: Minimize water usage | $5,887 | $4,200 | - | - |
$5,887
-
Tgal
|
- | - | |
| 09 | 3.7131: Use a rag recycle service | $425 | - | - | - | - |
$425
-
lb
|
- | |
| TOTAL RECOMMENDED | $20,698 | $18,100 |
$4,676
122,216
kWh
|
$2,248
-
kW-mo/yr
|
$5,887
-
Tgal
|
$425
-
lb
|
$7,462 | ||
| TOTAL IMPLEMENTED | $931 | - |
$931
16,706
kWh
|
- | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs