Assessment Year | 1999 |
---|---|
Principal Product | Precision turned components |
NAICS |
n/a
|
SIC | 3545: Cutting Tools, Machine Tool Accessories, and Machinists' Precision Measuring Devices |
Sales Range | $5 M to 10M |
# of Employees | 60 |
Plant Area |
30,000
ft2
|
Annual Production | 150,000
lb
|
Production Hrs. Annual | 4,500
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $43,314 | 543,962 |
kWh
|
$0.080 |
Electricity Demand | $20,958 | 2,118 |
kW-mo/yr
|
$9.90 |
Electricity Fees | $1,910 | - |
|
- |
Natural Gas | $8,831 | 638 |
MMBtu
|
$13.84 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $17,231 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,364 | $31,595 |
$7,032
88,511
kWh
|
$2,332
-
kW-mo/yr
|
- | - | - | |
02 | 2.4133: Use most efficient type of electric motors | $323 | $938 |
$323
16,120
kWh
|
- | - | - | - | |
03 | 2.7495: Install replacement doors | $1,799 | $700 | - | - |
$1,799
-
MMBtu
|
- | - | |
04 | 3.5311: Recover and reuse waste material | $5,258 | $500 | - | - | - | $5,258 | - | |
05 | 3.6192: Use a less expensive method of waste removal | $487 | $500 | - | - | - | - | $487 | |
TOTAL RECOMMENDED | $17,231 | $34,233 |
$7,355
104,631
kWh
|
$2,332
-
kW-mo/yr
|
$1,799
-
MMBtu
|
$5,258 | $487 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs