ITAC Assessment: HO0203
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Precision turned components
NAICS
n/a
SIC 3545: Cutting Tools, Machine Tool Accessories, and Machinists' Precision Measuring Devices
Sales Range $5
M
to 10
M
# of Employees 60
Plant Area 30,000
ft2
Annual Production 150,000
lb
Production Hrs. Annual 4,500
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $43,314 543,962
kWh
Electricity Demand $20,958 2,118
kW-mo/yr
Electricity Fees $1,910 -
Natural Gas $8,831 638
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,231 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $9,364 $31,595 $7,032
88,511
kWh
$2,332
-
kW-mo/yr
- - -
02 2.4133: Use most efficient type of electric motors $323 $938 $323
16,120
kWh
- - - -
03 2.7495: Install replacement doors $1,799 $700 - - $1,799
-
MMBtu
- -
04 3.5311: Recover and reuse waste material $5,258 $500 - - - $5,258 -
05 3.6192: Use a less expensive method of waste removal $487 $500 - - - - $487
TOTAL RECOMMENDED $17,231 $34,233 $7,355
104,631
kWh
$2,332
-
kW-mo/yr
$1,799
-
MMBtu
$5,258 $487
TOTAL IMPLEMENTED - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs