ITAC Assessment: HO0195
ITAC logo
ITAC Assessment: HO0195
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Boilers & Tanks
NAICS
n/a
SIC 3433: Heating Equipment, Except Electric and Warm Air Furnaces
Sales Range $10
M
to 50
M
# of Employees 275
Plant Area 27,000
ft2
Annual Production 550
pieces
Production Hrs. Annual 4,130
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $28,391 530,774
kWh
Electricity Demand $43,079 2,031
kW-mo/yr
Natural Gas $5,277 565
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $29,980 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,496

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $4,672 $9,033 $2,119
39,566
kWh
$2,553
-
kW-mo/yr
- - -
02 2.7111: Reduce illumination to minimum necessary levels $5,258 $150 $2,452
46,014
kWh
$2,806
-
kW-mo/yr
- - -
03 2.7229: Air condition only space necessary $2,914 - - - $2,914
-
MMBtu
- -
04 4.424: Improve space comfort conditioning $960 $3,000 - - - - $960
05 4.425: Eliminate/reduce redundant inspections $2,496 $5,000 - - - $2,496 -
06 4.514: Re-arrange equipment layout to reduce handling costs $6,240 $340 - - - - $6,240
07 4.621: Use fixtures to reduce machine changeout times $6,192 $5,000 - - - - $6,192
08 4.111: Add equipment/ operators to reduce production bottleneck $1,248 $2,500 - - - - $1,248
TOTAL RECOMMENDED $29,980 $25,023 $4,571
85,580
kWh
$5,359
-
kW-mo/yr
$2,914
-
MMBtu
$2,496 $14,640
TOTAL IMPLEMENTED $2,496 $5,000 - - - $2,496 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs