| Assessment Year | 1999 |
|---|---|
| Principal Product | Boilers & Tanks |
| NAICS |
n/a
|
| SIC | 3433: Heating Equipment, Except Electric and Warm Air Furnaces |
| Sales Range | $10 M to 50M |
| # of Employees | 275 |
| Plant Area |
27,000
ft2
|
| Annual Production | 550
pieces
|
| Production Hrs. Annual | 4,130
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $28,391 | 530,774 |
kWh
|
$0.053 |
| Electricity Demand | $43,079 | 2,031 |
kW-mo/yr
|
$21.21 |
| Natural Gas | $5,277 | 565 |
MMBtu
|
$9.34 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $29,980 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,496 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,672 | $9,033 |
$2,119
39,566
kWh
|
$2,553
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.7111: Reduce illumination to minimum necessary levels | $5,258 | $150 |
$2,452
46,014
kWh
|
$2,806
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.7229: Air condition only space necessary | $2,914 | - | - | - |
$2,914
-
MMBtu
|
- | - | |
| 04 | 4.424: Improve space comfort conditioning | $960 | $3,000 | - | - | - | - | $960 | |
| 05 | 4.425: Eliminate/reduce redundant inspections | $2,496 | $5,000 | - | - | - | $2,496 | - | |
| 06 | 4.514: Re-arrange equipment layout to reduce handling costs | $6,240 | $340 | - | - | - | - | $6,240 | |
| 07 | 4.621: Use fixtures to reduce machine changeout times | $6,192 | $5,000 | - | - | - | - | $6,192 | |
| 08 | 4.111: Add equipment/ operators to reduce production bottleneck | $1,248 | $2,500 | - | - | - | - | $1,248 | |
| TOTAL RECOMMENDED | $29,980 | $25,023 |
$4,571
85,580
kWh
|
$5,359
-
kW-mo/yr
|
$2,914
-
MMBtu
|
$2,496 | $14,640 | ||
| TOTAL IMPLEMENTED | $2,496 | $5,000 | - | - | - | $2,496 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs