| Assessment Year | 1999 |
|---|---|
| Principal Product | Primary Lithium Batteries |
| NAICS |
n/a
|
| SIC | 3692: Primary Batteries, Dry and Wet |
| Sales Range | $10 M to 50M |
| # of Employees | 410 |
| Plant Area |
43,000
ft2
|
| Annual Production | 6,750,000
pieces
|
| Production Hrs. Annual | 2,250
hrs
|
| Location (State) | New Jersey |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $55,313 | 1,128,957 |
kWh
|
$0.049 |
| Electricity Demand | $28,024 | 4,038 |
kW-mo/yr
|
$6.94 |
| Electricity Fees | $41,474 | - |
|
- |
| Natural Gas | $44,952 | 9,081 |
MMBtu
|
$4.95 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $24,831 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,014 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,539 | $8,289 |
$2,758
56,272
kWh
|
$781
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $409 | $1,120 |
$409
8,499
kWh
|
- | - | - | - | - | |
| 03 | 2.7231: Use radiant heater for spot heating | $2,678 | $4,800 | - | - |
$2,678
-
MMBtu
|
- | - | - | |
| 04 | 2.2511: Insulate bare equipment | $2,083 | $520 | - | - |
$2,083
-
MMBtu
|
- | - | - | |
| 05 | 2.7495: Install replacement doors | $562 | $700 | - | - |
$562
-
MMBtu
|
- | - | - | |
| 06 | 4.652: Replace existing equipment with more suitable substitutes | $960 | $600 | - | - | - | - | - | $960 | |
| 07 | 4.111: Add equipment/ operators to reduce production bottleneck | $6,000 | $5,000 | - | - | - | - | - | $6,000 | |
| 08 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $1,200 | $1,000 | - | - | - |
$1,200
-
lb
|
- | - | |
| 09 | 3.5217: Reuse / recycle/ sell paper products | $2,400 | $1,000 | - | - | - |
$2,400
-
lb
|
- | - | |
| 10 | 3.1191: Change procedures / equipment / operating conditions | $5,000 | $1,000 | - | - | - | - |
$5,000
-
lb
|
- | |
| TOTAL RECOMMENDED | $24,831 | $24,029 |
$3,167
64,771
kWh
|
$781
-
kW-mo/yr
|
$5,323
-
MMBtu
|
$3,600
-
lb
|
$5,000
-
lb
|
$6,960 | ||
| TOTAL IMPLEMENTED | $9,014 | $3,940 |
$409
8,499
kWh
|
- |
$2,645
-
MMBtu
|
- |
$5,000
-
lb
|
$960 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs