Assessment Year | 1999 |
---|---|
Principal Product | Paintbrush Handles |
NAICS |
n/a
|
SIC | 2499: Wood Products, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 50 |
Plant Area |
40,000
ft2
|
Annual Production | 6,500,000
pieces
|
Production Hrs. Annual | 2,500
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $39,198 | 667,937 |
kWh
|
$0.059 |
Electricity Demand | $92,089 | 4,074 |
kW-mo/yr
|
$22.60 |
Electricity Fees | $7,882 | - |
|
- |
Fuel Oil #4 | $15,000 | 3,500 |
MMBtu
|
$4.29 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $13,337 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,443 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #4 Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,167 | $5,870 |
$757
12,896
kWh
|
$1,410
-
kW-mo/yr
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,826 | $120 |
$1,826
31,067
kWh
|
- | - | - | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $364 | $410 |
$364
6,155
kWh
|
- | - | - | |
04 | 2.5122: Replace high resistance ducts, pipes, and fittings | $875 | $400 |
$875
14,947
kWh
|
- | - | - | |
05 | 2.7496: Install partitions to reduce size of conditioned space | $1,245 | $1,500 | - | - |
$1,245
-
MMBtu
|
- | |
06 | 4.444: Install system to collect scrap | $4,160 | $1,320 | - | - | - | $4,160 | |
07 | 3.1191: Change procedures / equipment / operating conditions | $1,125 | $500 | - | - | - | $1,125 | |
08 | 3.1191: Change procedures / equipment / operating conditions | $450 | $1,000 | - | - | - | $450 | |
09 | 3.1191: Change procedures / equipment / operating conditions | $1,125 | $1,000 | - | - | - | $1,125 | |
TOTAL RECOMMENDED | $13,337 | $12,120 |
$3,822
65,065
kWh
|
$1,410
-
kW-mo/yr
|
$1,245
-
MMBtu
|
$6,860 | ||
TOTAL IMPLEMENTED | $6,443 | $7,890 |
$3,458
58,910
kWh
|
$1,410
-
kW-mo/yr
|
- | $1,575 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #4 Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs