| Assessment Year | 1998 |
|---|---|
| Principal Product | Electrical Products |
| NAICS |
n/a
|
| SIC | 3629: Electrical Industrial Apparatus, Not Elsewhere Classified |
| Sales Range | $1 M to 5M |
| # of Employees | 50 |
| Plant Area |
35,000
ft2
|
| Annual Production | 0
pieces
|
| Production Hrs. Annual | 2,080
hrs
|
| Location (State) | New Jersey |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $68,217 | 804,513 |
kWh
|
$0.085 |
| Electricity Demand | $30,074 | 3,452 |
kW-mo/yr
|
$8.71 |
| Electricity Fees | $4,869 | - |
|
- |
| Natural Gas | $44,787 | 8,214 |
MMBtu
|
$5.45 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $40,259 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,124 | $17,821 |
$3,825
45,135
kWh
|
$2,299
-
kW-mo/yr
|
- | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,250 | $1,569 |
$784
9,379
kWh
|
$466
-
kW-mo/yr
|
- | - | |
| 03 | 2.7111: Reduce illumination to minimum necessary levels | $3,033 | $120 |
$1,904
22,274
kWh
|
$1,129
-
kW-mo/yr
|
- | - | |
| 04 | 2.7135: Install occupancy sensors | $2,983 | $600 |
$2,983
35,170
kWh
|
- | - | - | |
| 05 | 2.2414: Use waste heat from hot flue gases to preheat | $648 | $1,073 | - | - |
$648
-
MMBtu
|
- | |
| 06 | 2.2136: Install / repair insulation on steam lines | $492 | $1,214 | - | - |
$492
-
MMBtu
|
- | |
| 07 | 4.211: Consider use / purchase of bulk materials where possible | $4,478 | $500 | - | - | - | $4,478 | |
| 08 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $19,788 | $500 | - |
$19,788
-
kW-mo/yr
|
- | - | |
| 09 | 2.3191: Use demand controller or load shedder | $1,463 | - | - |
$1,463
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $40,259 | $23,397 |
$9,496
111,958
kWh
|
$25,145
-
kW-mo/yr
|
$1,140
-
MMBtu
|
$4,478 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs