ITAC Assessment: HO0147
ITAC logo
ITAC Assessment: HO0147
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Powder coating
NAICS
n/a
SIC 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 27
Plant Area 17,000
ft2
Annual Production 100,000
lb
Production Hrs. Annual 3,172
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $22,559 240,621
kWh
Electricity Demand $10,307 1,264
kW-mo/yr
Electricity Fees $(-5,665.0) -
Natural Gas $42,705 8,990
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $30,387 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,474

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 2.4133: Use most efficient type of electric motors $163 $260 $163
1,758
kWh
- - -
02 2.2511: Insulate bare equipment $1,474 $2,500 - $1,474
-
MMBtu
- -
03 3.6193: Install equipment (eg compactor) to reduce disposal costs $2,400 $6,500 - - $2,400
-
lb
-
04 2.7134: Use photocell controls $850 $1,200 $850
9,086
kWh
- - -
05 3.5311: Recover and reuse waste material $500 - - - $500
-
lb
-
06 4.513: Re-arrange equipment layout to reduce labor costs $25,000 - - - - $25,000
TOTAL RECOMMENDED $30,387 $10,460 $1,013
10,844
kWh
$1,474
-
MMBtu
$2,900
-
lb
$25,000
TOTAL IMPLEMENTED $1,474 $2,500 - $1,474
-
MMBtu
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs