ITAC Assessment: HO0143
ITAC logo
ITAC Assessment: HO0143
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Retail Plastic Bags
NAICS
n/a
SIC 3081: Unsupported Plastics Film and Sheet
Sales Range $1
M
to 5
M
# of Employees 40
Plant Area 40,000
ft2
Annual Production 2,000,000
lb
Production Hrs. Annual 4,080
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $50,307 880,129
kWh
Electricity Demand $76,651 3,350
kW-mo/yr
Electricity Fees $10,726 -
Natural Gas $3,944 263
MMBtu
Fuel Oil #2 $11,755 2,330
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $67,688 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $47,443

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,952 $4,592 $1,854
31,360
kWh
$1,098
-
kW-mo/yr
- - -
02 2.4133: Use most efficient type of electric motors $618 $1,160 $618
10,844
kWh
- - - -
03 2.4221: Install compressor air intakes in coolest locations $679 $400 $416
7,327
kWh
$263
-
kW-mo/yr
- - -
04 3.6193: Install equipment (eg compactor) to reduce disposal costs $2,568 $6,500 - - - $2,568
-
lb
-
05 4.125: $3,592 $23,000 $(-1,448.0)
(-25,205)
kWh
- - - $5,040
06 3.1191: Change procedures / equipment / operating conditions $15,974 - - $31,574
-
kW-mo/yr
- $9,400
-
lb
$(-25,000.0)
07 4.812: Apply for investment incentives $41,305 $100 - - $41,305 - -
TOTAL RECOMMENDED $67,688 $35,752 $1,440
24,326
kWh
$32,935
-
kW-mo/yr
$41,305 $11,968
-
lb
$(-19,960.0)
TOTAL IMPLEMENTED $47,443 $12,352 $2,472
42,204
kWh
$1,098
-
kW-mo/yr
$41,305 $2,568
-
lb
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs