Assessment Year | 1996 |
---|---|
Principal Product | Textile Dyers |
NAICS |
n/a
|
SIC | 2269: Finishers of Textiles, Not elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 50 |
Plant Area |
20,000
ft2
|
Annual Production | 8,000,000
lb
|
Production Hrs. Annual | 8,730
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $43,973 | 762,310 |
kWh
|
$0.058 |
Electricity Demand | $15,348 | 1,680 |
kW-mo/yr
|
$9.14 |
Electricity Fees | $7,465 | - |
|
- |
Natural Gas | $301,024 | 89,680 |
MMBtu
|
$3.36 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $108,999 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $96,937 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,509 | $16,309 |
$4,303
74,736
kWh
|
$1,206
-
kW-mo/yr
|
- | - | |
02 | 2.4133: Use most efficient type of electric motors | $688 | $937 |
$688
12,016
kWh
|
- | - | - | |
03 | 2.7135: Install occupancy sensors | $122 | $400 |
$122
2,052
kWh
|
- | - | - | |
04 | 2.2414: Use waste heat from hot flue gases to preheat | $23,949 | $13,764 | - | - |
$23,949
-
MMBtu
|
- | |
05 | 2.2136: Install / repair insulation on steam lines | $5,862 | $2,993 | - | - |
$5,862
-
MMBtu
|
- | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $569 | $560 |
$569
9,672
kWh
|
- | - | - | |
07 | 3.4112: Recovery metals from rinse water(evap., ion exchange, ro, electrolysis, electrodialysis) and reuse rinse water | $72,300 | $287,000 | - | - | - |
$72,300
-
Tgal
|
|
TOTAL RECOMMENDED | $108,999 | $321,963 |
$5,682
98,476
kWh
|
$1,206
-
kW-mo/yr
|
$29,811
-
MMBtu
|
$72,300
-
Tgal
|
||
TOTAL IMPLEMENTED | $96,937 | $301,701 |
$688
12,016
kWh
|
- |
$23,949
-
MMBtu
|
$72,300
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs