ITAC Assessment: HO0129
ITAC logo
ITAC Assessment: HO0129
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Cheese and Food Packaging
NAICS
n/a
SIC 2022: Natural, Processed, and Imitation Cheese
Sales Range $10
M
to 50
M
# of Employees 110
Plant Area 6,000,000
ft2
Annual Production 500
pieces
Production Hrs. Annual 2,340
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $103,364 1,813,892
kWh
Electricity Demand $113,043 4,872
kW-mo/yr
Electricity Fees $14,787 -
Natural Gas $59,258 10,204
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $24,893 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $22,089

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $7,789 $10,234 $2,523
44,256
kWh
$5,266
-
kW-mo/yr
- -
02 2.7135: Install occupancy sensors $713 $400 $713
12,603
kWh
- - -
03 2.4133: Use most efficient type of electric motors $246 $292 $80
1,465
kWh
$166
-
kW-mo/yr
- -
04 2.2414: Use waste heat from hot flue gases to preheat $2,804 $2,220 - - $2,804
-
MMBtu
-
05 2.1233: Analyze flue gas for proper air/fuel ratio $2,150 $2,200 - - $2,150
-
MMBtu
-
06 3.5212: Regrind, reuse, or sell scrap plastic parts $11,191 $20,000 - - - $11,191
-
lb
TOTAL RECOMMENDED $24,893 $35,346 $3,316
58,324
kWh
$5,432
-
kW-mo/yr
$4,954
-
MMBtu
$11,191
-
lb
TOTAL IMPLEMENTED $22,089 $33,126 $3,316
58,324
kWh
$5,432
-
kW-mo/yr
$2,150
-
MMBtu
$11,191
-
lb
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs