Assessment Year | 1995 |
---|---|
Principal Product | Cosmetics |
NAICS |
n/a
|
SIC | 2844: Perfumes, Cosmetics, and Other Toilet Preparations |
Sales Range | $100 M to 500M |
# of Employees | 225 |
Plant Area |
200,000
ft2
|
Annual Production | 50,000,000
pieces
|
Production Hrs. Annual | 6,480
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $624,507 | 7,325,029 |
kWh
|
$0.085 |
Natural Gas | $83,440 | 26,832 |
MMBtu
|
$3.11 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $23,837 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $16,607 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,238 | $2,300 |
$3,238
38,101
kWh
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,814 | $7,694 |
$2,814
33,118
kWh
|
- | - | |
03 | 2.1232: Keep boiler tubes clean | $5,227 | $220 | - |
$5,227
-
MMBtu
|
- | |
04 | 2.2136: Install / repair insulation on steam lines | $383 | $513 | - |
$383
-
MMBtu
|
- | |
05 | 2.4235: Remove or close off unneeded compressed air lines | $1,237 | $500 |
$1,237
14,654
kWh
|
- | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,328 | $250 |
$5,328
62,427
kWh
|
- | - | |
07 | 3.4114: Replace city water with recycled water via cooling tower | $5,610 | $4,000 | - | - |
$5,610
-
Tgal
|
|
TOTAL RECOMMENDED | $23,837 | $15,477 |
$12,617
148,300
kWh
|
$5,610
-
MMBtu
|
$5,610
-
Tgal
|
||
TOTAL IMPLEMENTED | $16,607 | $10,464 |
$11,380
133,646
kWh
|
$5,227
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs