ITAC Assessment: HO0117
ITAC logo
ITAC Assessment: HO0117
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Cosmetics
NAICS
n/a
SIC 2844: Perfumes, Cosmetics, and Other Toilet Preparations
Sales Range $100
M
to 500
M
# of Employees 225
Plant Area 200,000
ft2
Annual Production 50,000,000
pieces
Production Hrs. Annual 6,480
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $624,507 7,325,029
kWh
Natural Gas $83,440 26,832
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $23,837 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,607

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Disposal Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $3,238 $2,300 $3,238
38,101
kWh
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,814 $7,694 $2,814
33,118
kWh
- -
03 2.1232: Keep boiler tubes clean $5,227 $220 - $5,227
-
MMBtu
-
04 2.2136: Install / repair insulation on steam lines $383 $513 - $383
-
MMBtu
-
05 2.4235: Remove or close off unneeded compressed air lines $1,237 $500 $1,237
14,654
kWh
- -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,328 $250 $5,328
62,427
kWh
- -
07 3.4114: Replace city water with recycled water via cooling tower $5,610 $4,000 - - $5,610
-
Tgal
TOTAL RECOMMENDED $23,837 $15,477 $12,617
148,300
kWh
$5,610
-
MMBtu
$5,610
-
Tgal
TOTAL IMPLEMENTED $16,607 $10,464 $11,380
133,646
kWh
$5,227
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Water Disposal Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs