ITAC Assessment: HO0115
ITAC logo
ITAC Assessment: HO0115
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Candy
NAICS
n/a
SIC 2064: Candy and Other Confectionery Products
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area 100,000
ft2
Annual Production 35,000,000
lb
Production Hrs. Annual 4,160
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $405,387 2,911,196
kWh
Natural Gas $146,747 28,648
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $26,074 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $776 $1,011 $776
5,569
kWh
- - -
02 2.1232: Keep boiler tubes clean $2,569 $2,800 - $2,569
-
MMBtu
- -
03 2.7135: Install occupancy sensors $2,276 $400 $2,276
14,361
kWh
- - -
04 2.2136: Install / repair insulation on steam lines $583 $250 - $583
-
MMBtu
- -
05 2.8114: Change rate schedules or other changes in utility service $12,913 $8,000 - - - $12,913
06 3.4114: Replace city water with recycled water via cooling tower $6,957 $4,000 - - $6,957
-
Tgal
-
TOTAL RECOMMENDED $26,074 $16,461 $3,052
19,930
kWh
$3,152
-
MMBtu
$6,957
-
Tgal
$12,913
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs