Assessment Year | 1995 |
---|---|
Principal Product | Molded Plastic Parts |
NAICS |
n/a
|
SIC | 3641: Electric Lamp Bulbs and Tubes |
Sales Range | $5 M to 10M |
# of Employees | 90 |
Plant Area |
70,000
ft2
|
Annual Production | 1,800,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $151,327 | 1,064,478 |
kWh
|
$0.14 |
Natural Gas | $57,168 | 7,203 |
MMBtu
|
$7.94 |
Fuel Oil #2 | $14,173 | 2,223 |
MMBtu
|
$6.38 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $25,507 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $15,483 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,587 | $5,326 |
$5,587
39,273
kWh
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $509 | $320 |
$509
3,517
kWh
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,804 | $350 | - |
$7,804
-
MMBtu
|
- | |
04 | 2.4133: Use most efficient type of electric motors | $683 | $680 |
$683
4,689
kWh
|
- | - | |
05 | 2.1232: Keep boiler tubes clean | $723 | $2,000 | - | - |
$723
-
MMBtu
|
|
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $686 | $315 |
$686
4,982
kWh
|
- | - | |
07 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $9,515 | $19,000 |
$12,496
87,925
kWh
|
$(-2,981.0)
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $25,507 | $27,991 |
$19,961
140,386
kWh
|
$4,823
-
MMBtu
|
$723
-
MMBtu
|
||
TOTAL IMPLEMENTED | $15,483 | $8,671 |
$6,956
48,944
kWh
|
$7,804
-
MMBtu
|
$723
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs