ITAC Assessment: HO0078
ITAC logo
ITAC Assessment: HO0078
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Dyeing and finishing fabrics
NAICS
n/a
SIC 2258: Lace and Warp Knit Fabric Mills
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 100,000
ft2
Annual Production 120,000
thousand feet
Production Hrs. Annual 5,000
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $716,386 8,348,769
kWh
Natural Gas $762,352 194,758
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $14,159 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,650

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $5,943 $5,010 $5,943
69,168
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,524 $3,277 $2,524
29,308
kWh
-
03 2.4133: Use most efficient type of electric motors $3,930 $5,390 $3,930
45,721
kWh
-
04 2.4221: Install compressor air intakes in coolest locations $1,509 $800 $1,509
17,585
kWh
-
05 2.2136: Install / repair insulation on steam lines $253 $113 - $253
-
MMBtu
TOTAL RECOMMENDED $14,159 $14,590 $13,906
161,782
kWh
$253
-
MMBtu
TOTAL IMPLEMENTED $12,650 $13,790 $12,397
144,197
kWh
$253
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs