ITAC Assessment: HO0012
ITAC logo
ITAC Assessment: HO0012
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product DESK PADS AND TRAYS
NAICS
n/a
SIC 2678: Stationery, Tablets, and Related Products
Sales Range $5
M
to 10
M
# of Employees 95
Plant Area
n/a
Annual Production 1,000,000
pieces
Production Hrs. Annual 2,210
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $26,019 177,315
kWh
Natural Gas $5,144 730
MMBtu
Fuel Oil #2 $8,756 946
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,627 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $213 $123 $243
1,465
kWh
$(-30.0)
02 2.4133: Use most efficient type of electric motors $272 $354 $272
1,758
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $47 $(-360.0) $47
293
kWh
-
04 2.8121: Apply for tax-free status for energy purchases $606 $200 $606
-
kWh
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $904 $2,650 $904
11,137
kWh
-
06 2.6218: Turn off equipment when not in use $300 - $300
2,345
kWh
-
07 2.8114: Change rate schedules or other changes in utility service $2,285 - $2,285
-
kWh
-
TOTAL RECOMMENDED $4,627 $2,967 $4,657
16,998
kWh
$(-30.0)
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs