ITAC Assessment: GT1003
ITAC logo
ITAC Assessment: GT1003
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product Truck and Agriculture Rubber Mats
NAICS 326299: All Other Rubber Product Manufacturing
SIC 3061: Molded, Extruded, and Lathe-Cut Mechanical Rubber Goods
Sales Range $10
M
to 50
M
# of Employees 42
Plant Area 104,800
ft2
Annual Production 141,003
units
Production Hrs. Annual 4,300
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $306,919 2,662,800
kWh
Natural Gas $136,155 28,248
MMBtu
TOTAL YEARLY COSTS $443,074
RECOMMENDED SAVINGS* $275,884 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Personnel Changes Savings
01 2.2694: Use highest temperature for chilling or cold storage $1,244 $400 $1,244
10,820
kWh
- -
02 2.6218: Turn off equipment when not in use $19,447 $6,600 $492
4,279
kWh
$18,955
-
MMBtu
-
03 2.4231: Reduce the pressure of compressed air to the minimum required $5,754 $2,400 $5,754
50,031
kWh
- -
04 2.7224: Reduce space conditioning during non-working hours $1,117 $600 $1,117
9,714
kWh
- -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,175 $1,850 $5,075
44,133
kWh
- $(-2,900.0)
06 2.6212: Turn off equipment during breaks, reduce operating time $1,390 $1,495 $1,390
12,085
kWh
- -
07 2.2135: Repair and eliminate steam leaks $1,657 $1,850 - $2,877
-
MMBtu
$(-1,220.0)
08 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $18,909 $61,212 $18,909
164,424
kWh
- -
09 2.3413: Burn fossil fuel to produce steam to drive a steam turbine-generator and use steam exhaust for heat $107,574 $414,000 $126,500
1,100,000
kWh
$(-18,926.0)
-
MMBtu
-
10 2.9114: Use solar heat to make electricty $116,617 $694,521 $116,617
1,011,757
kWh
- -
TOTAL RECOMMENDED $275,884 $1,184,928 $277,098
2,407,243
kWh
$2,906
-
MMBtu
$(-4,120.0)
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs