| Assessment Year | 2026 |
|---|---|
| Principal Product | Fuel, Vegetable + Tall Oil, Caustic Acid |
| NAICS | 325998: All Other Miscellaneous Chemical Product and Preparation Manufacturing |
| SIC | 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified |
| Sales Range | $100 M to 500M |
| # of Employees | 275 |
| Plant Area |
300,000
ft2
|
| Annual Production | 221,306
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $817,823 | 6,680,489 |
kWh
|
$0.12 |
| Electricity Fees | $67,427 | - |
|
- |
| Natural Gas | $338,953 | 69,065 |
MMBtu
|
$4.91 |
| TOTAL YEARLY COSTS | $1,224,203 | |||
| RECOMMENDED SAVINGS* | $386,687 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.8121: Apply for tax-free status for energy purchases | $55,610 | $400 | - | $55,610 | - | - | - | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,312 | $200 |
$3,312
27,148
kWh
|
- | - | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,557 | $1,850 |
$5,457
44,730
kWh
|
- | - | $(-2,900.0) | - | |
| 04 | 4.212: Adopt in-house material generation | $88,408 | $75,000 |
$(-8,971.7)
(-73,539)
kWh
|
- | - | - | $97,380 | |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,128 | $6,214 |
$5,128
42,035
kWh
|
- | - | - | - | |
| 06 | 2.2136: Install / repair insulation on steam lines | $1,088 | $2,460 | - | - |
$1,088
-
MMBtu
|
- | - | |
| 07 | 2.3413: Burn fossil fuel to produce steam to drive a steam turbine-generator and use steam exhaust for heat | $228,801 | $603,750 |
$267,180
2,190,000
kWh
|
- |
$(-38,379.0)
-
MMBtu
|
- | - | |
| 08 | 2.3212: Optimize plant power factor | $1,783 | $8,009 | - | $1,783 | - | - | - | |
| TOTAL RECOMMENDED | $386,687 | $697,883 |
$272,105
2,230,374
kWh
|
$57,393 |
$(-37,291.0)
-
MMBtu
|
$(-2,900.0) | $97,380 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs