ITAC Assessment: GT0999
ITAC logo
ITAC Assessment: GT0999
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Pressure Sensitive Labels, Tapes, Die Cut Components
NAICS 323111: Commercial Printing (except Screen and Books)
SIC 2759: Commercial Printing, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 30
Plant Area 55,000
ft2
Annual Production 31,574
thousand feet
Production Hrs. Annual 4,800
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $63,671 774,400
kWh
Electricity Demand $36,648 2,041
kW-mo/yr
Natural Gas $5,341 484
MMBtu
TOTAL YEARLY COSTS $105,660
RECOMMENDED SAVINGS* $38,939 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,673 $1,850 $8,106
98,855
kWh
$467
-
kW-mo/yr
$(-2,900.0)
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,068 $2,504 $1,008
12,308
kWh
$59
-
kW-mo/yr
-
03 2.4231: Reduce the pressure of compressed air to the minimum required $85 $200 $80
981
kWh
$4
-
kW-mo/yr
-
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,830 $10,000 $2,683
32,724
kWh
$147
-
kW-mo/yr
-
05 2.9114: Use solar heat to make electricty $29,283 $207,473 $25,386
308,811
kWh
$3,897
-
kW-mo/yr
-
TOTAL RECOMMENDED $38,939 $222,027 $37,264
453,679
kWh
$4,575
-
kW-mo/yr
$(-2,900.0)
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs