Assessment Year | 2024 |
---|---|
Principal Product | Diesel Engines |
NAICS | 335312: Motor and Generator Manufacturing |
SIC | 3621: Motors and Generators |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
68,000
ft2
|
Annual Production | 20,695
units
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $200,631 | 1,403,703 |
kWh
|
$0.14 |
Natural Gas | $23,582 | 2,892 |
MMBtu
|
$8.15 |
TOTAL YEARLY COSTS | $224,213 | |||
RECOMMENDED SAVINGS* | $109,489 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $29,398 | $1,850 |
$32,298
230,703
kWh
|
$(-2,900.0) | |
02 | 2.4239: Eliminate or reduce compressed air usage | $1,518 | $100 |
$1,518
10,839
kWh
|
- | |
03 | 2.6218: Turn off equipment when not in use | $7,859 | $1,800 |
$7,859
56,138
kWh
|
- | |
04 | 2.6211: Conserve energy by efficient use of vending machines | $369 | $90 |
$369
2,632
kWh
|
- | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,073 | $800 |
$2,073
14,806
kWh
|
- | |
06 | 2.6218: Turn off equipment when not in use | $827 | $1,740 |
$827
5,909
kWh
|
- | |
07 | 2.7135: Install occupancy sensors | $339 | $875 |
$339
2,421
kWh
|
- | |
08 | 2.9114: Use solar heat to make electricty | $67,106 | $614,572 |
$67,106
479,932
kWh
|
- | |
TOTAL RECOMMENDED | $109,489 | $621,827 |
$112,389
803,380
kWh
|
$(-2,900.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs