Assessment Year | 2024 |
---|---|
Principal Product | Lead-Acid Batteries |
NAICS | 335911: Storage Battery Manufacturing |
SIC | 3694: Electrical Equipment for Internal Combustion Engines |
Sales Range | $100 M to 500M |
# of Employees | 117 |
Plant Area |
167,000
ft2
|
Annual Production | 786,467
units
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,827,935 | 25,538,658 |
kWh
|
$0.072 |
Natural Gas | $225,201 | 26,698 |
MMBtu
|
$8.44 |
Other Gas | $16,682 | 1 |
MMBtu
|
$16,681.68 |
TOTAL YEARLY COSTS | $2,069,818 | |||
RECOMMENDED SAVINGS* | $395,591 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.8121: Apply for tax-free status for energy purchases | $14,430 | $400 | - | $14,430 | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $46,530 | $1,850 |
$49,430
686,522
kWh
|
- | $(-2,900.0) | |
03 | 2.7135: Install occupancy sensors | $647 | $390 |
$647
8,986
kWh
|
- | - | |
04 | 2.6211: Conserve energy by efficient use of vending machines | $292 | $270 |
$292
4,061
kWh
|
- | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $23,328 | $36,015 |
$23,328
324,000
kWh
|
- | - | |
06 | 2.9114: Use solar heat to make electricty | $310,364 | $5,706,740 |
$310,364
4,336,196
kWh
|
- | - | |
TOTAL RECOMMENDED | $395,591 | $5,745,665 |
$384,061
5,359,765
kWh
|
$14,430 | $(-2,900.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs