ITAC Assessment: GT0968
ITAC logo
ITAC Assessment: GT0968
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product School Buses
NAICS 336211: Motor Vehicle Body Manufacturing
SIC 3713: Truck and Bus Bodies
Sales Range greater than $500
M
# of Employees 1,200
Plant Area 1,000,000
ft2
Annual Production 6,727
units
Production Hrs. Annual 2,500
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,522,135 21,337,881
kWh
Natural Gas $933,982 103,204
MMBtu
TOTAL YEARLY COSTS $2,456,117
RECOMMENDED SAVINGS* $405,892 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $246,074

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Personnel Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $64,657 $1,850 $67,557
965,109
kWh
$(-2,900.0)
02 2.6218: Turn off equipment when not in use $104,725 $13,000 $104,725
1,475,000
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $73,640 $23,680 $73,640
1,037,184
kWh
-
04 2.6218: Turn off equipment when not in use $3,052 $3,250 $3,052
42,981
kWh
-
05 2.9114: Use solar heat to make electricty $159,818 $4,611,930 $159,818
2,240,394
kWh
-
TOTAL RECOMMENDED $405,892 $4,653,710 $408,792
5,760,668
kWh
$(-2,900.0)
TOTAL IMPLEMENTED $246,074 $41,780 $248,974
3,520,274
kWh
$(-2,900.0)
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs