ITAC Assessment: GT0967
ITAC logo
ITAC Assessment: GT0967
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Aluminum Extrusions
NAICS 331318: Other Aluminum Rolling, Drawing, and Extruding
SIC 3354: Aluminum Extruded Products
Sales Range $50
M
to 100
M
# of Employees 165
Plant Area 150,000
ft2
Annual Production 37,068,142
units
Production Hrs. Annual 7,200
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $869,031 8,686,123
kWh
Natural Gas $434,665 67,475
MMBtu
TOTAL YEARLY COSTS $1,303,696
RECOMMENDED SAVINGS* $323,753 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $77,908

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Personnel Changes Savings
01 2.8121: Apply for tax-free status for energy purchases $23,763 $800 - $23,763 -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $48,377 $1,850 $51,277
512,766
kWh
- $(-2,900.0)
03 2.7224: Reduce space conditioning during non-working hours $4,800 $1,000 $4,800
47,800
kWh
- -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $968 $576 $968
9,681
kWh
- -
05 2.4323: Use optimum size and capacity equipment $5,843 $24,000 $5,843
58,429
kWh
- -
06 2.9114: Use solar heat to make electricty $237,120 $2,593,008 $237,120
2,370,049
kWh
- -
07 2.3212: Optimize plant power factor $2,881 $13,403 - $2,881 -
TOTAL RECOMMENDED $323,753 $2,634,637 $300,008
2,998,725
kWh
$26,644 $(-2,900.0)
TOTAL IMPLEMENTED $77,908 $4,226 $57,045
570,247
kWh
$23,763 $(-2,900.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Fees Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs