Assessment Year | 2021 |
---|---|
Principal Product | Aluminum Architectural Products |
NAICS | 332321: Metal Window and Door Manufacturing |
SIC | 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing |
Sales Range | $100 M to 500M |
# of Employees | 427 |
Plant Area |
1,200,000
ft2
|
Annual Production | 13,229
ton
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,635,936 | 35,364,914 |
kWh
|
$0.075 |
Natural Gas | $785,473 | 162,298 |
MMBtu
|
$4.84 |
LPG | $46,484 | 4,569 |
MMBtu
|
$10.17 |
TOTAL YEARLY COSTS | $3,467,893 | |||
RECOMMENDED SAVINGS* | $515,260 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $265,804 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.6218: Turn off equipment when not in use | $79,957 | $675 |
$79,957
1,072,735
kWh
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $126,097 | $4,500 |
$126,097
1,726,128
kWh
|
- | - | |
03 | 2.2625: Chill water to the highest temperature possible | $18,092 | $2,000 |
$18,092
242,842
kWh
|
- | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,307 | $2,255 |
$2,307
30,972
kWh
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $54,280 | $66,564 |
$54,280
728,592
kWh
|
- | - | |
06 | 2.7135: Install occupancy sensors | $21,155 | $29,319 |
$21,155
283,960
kWh
|
- | - | |
07 | 2.2437: Recover waste heat from equipment | $3,162 | $4,561 | - | - |
$3,162
-
MMBtu
|
|
08 | 2.3212: Optimize plant power factor | $9,097 | $34,730 | - | $9,097 | - | |
09 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $201,113 | $1,989,215 |
$336,064
6,223,400
kWh
|
- |
$(-134,951.0)
-
MMBtu
|
|
TOTAL RECOMMENDED | $515,260 | $2,133,820 |
$637,953
10,308,629
kWh
|
$9,097 |
$(-131,789.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | $265,804 | $78,556 |
$262,642
3,558,427
kWh
|
- |
$3,162
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs