| Assessment Year | 2020 |
|---|---|
| Principal Product | TABOREX 1108 |
| NAICS | 325211: Plastics Material and Resin Manufacturing |
| SIC | 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers |
| Sales Range | $5 M to 10M |
| # of Employees | 22 |
| Plant Area |
45,220
ft2
|
| Annual Production | 3,776,000
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $276,232 | 2,910,600 |
kWh
|
$0.095 |
| TOTAL YEARLY COSTS | $276,232 | |||
| RECOMMENDED SAVINGS* | $117,255 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $46,478 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2625: Chill water to the highest temperature possible | $4,870 | $250 |
$4,870
51,269
kWh
|
- | |
| 02 | 2.7135: Install occupancy sensors | $16,405 | $3,377 |
$16,405
172,681
kWh
|
- | |
| 03 | 2.6218: Turn off equipment when not in use | $3,914 | $1,050 |
$6,514
68,568
kWh
|
$(-2,600.0) | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $21,289 | $12,280 |
$21,289
224,091
kWh
|
- | |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,055 | $9,579 |
$7,055
74,259
kWh
|
- | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $570 | $1,430 |
$570
6,002
kWh
|
- | |
| 07 | 2.9114: Use solar heat to make electricty | $63,153 | $568,008 |
$63,153
665,422
kWh
|
- | |
| TOTAL RECOMMENDED | $117,255 | $595,974 |
$119,855
1,262,292
kWh
|
$(-2,600.0) | ||
| TOTAL IMPLEMENTED | $46,478 | $16,957 |
$49,078
516,609
kWh
|
$(-2,600.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs