ITAC Assessment: GT0932
ITAC logo
ITAC Assessment: GT0932
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Bedding/Sheeting Textiles
NAICS 313310: Textile and Fabric Finishing Mills
SIC 2221: Broadwoven Fabric Mills, Manmade Fiber and Silk
Sales Range $1
M
to 5
M
# of Employees 12
Plant Area 125,000
ft2
Annual Production 12,000
thousand feet
Production Hrs. Annual 2,496
hrs
Location (State) South Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $76,579 685,824
kWh
Natural Gas $124,613 23,915
MMBtu
TOTAL YEARLY COSTS $201,192
RECOMMENDED SAVINGS* $19,466 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,181

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2135: Repair and eliminate steam leaks $2,019 $500 $2,019
18,357
kWh
-
02 2.2511: Insulate bare equipment $495 $382 - $495
-
MMBtu
03 2.7135: Install occupancy sensors $1,606 $1,689 $1,606
14,602
kWh
-
04 2.2511: Insulate bare equipment $4,768 $5,877 - $4,768
-
MMBtu
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $899 $1,117 $899
8,174
kWh
-
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $9,678 $14,251 $9,678
87,986
kWh
-
TOTAL RECOMMENDED $19,466 $23,815 $14,203
129,118
kWh
$5,263
-
MMBtu
TOTAL IMPLEMENTED $8,181 $7,875 $2,918
26,531
kWh
$5,263
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs