ITAC Assessment: GT0905
ITAC logo
ITAC Assessment: GT0905
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product HPP Processed Product & Cold Storage
NAICS 311991: Perishable Prepared Food Manufacturing
SIC 2099: Food Preparations, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 60
Plant Area 90,000
ft2
Annual Production 35,000,000
lb
Production Hrs. Annual 7,200
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $209,845 4,004,782
kWh
Natural Gas $16,180 939
MMBtu
TOTAL YEARLY COSTS $226,024
RECOMMENDED SAVINGS* $5,732 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,694

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7135: Install occupancy sensors $2,333 $700 $2,333
46,656
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $3,361 $8,865 $3,361
67,226
kWh
03 4.514: Re-arrange equipment layout to reduce handling costs $38 $107 $38
753
kWh
TOTAL RECOMMENDED $5,732 $9,672 $5,732
114,635
kWh
TOTAL IMPLEMENTED $5,694 $9,565 $5,694
113,882
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs