ITAC Assessment: GT0888
ITAC logo
ITAC Assessment: GT0888
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Doors, Window, and Other
NAICS 331318: Other Aluminum Rolling, Drawing, and Extruding
SIC 3354: Aluminum Extruded Products
Sales Range $100
M
to 500
M
# of Employees 345
Plant Area 900,000
ft2
Annual Production 10,000
ton
Production Hrs. Annual 4,500
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,448,947 25,939,241
kWh
Electricity Demand $593,404 52,017
kW-mo/yr
Electricity Fees $450,705 -
Natural Gas $776,819 104,582
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $96,889 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
01 2.4314: Use synthetic lubricant $32,596 - $22,535
441,000
kWh
$10,061
-
kW-mo/yr
- -
02 2.6212: Turn off equipment during breaks, reduce operating time $100 - $100
1,966
kWh
- - -
03 2.7111: Reduce illumination to minimum necessary levels $2,563 $2,250 $1,962
30,510
kWh
$601
-
kW-mo/yr
- -
04 2.2531: Re-size charging openings or add movable cover or door $2,915 $1,680 - - $2,915
-
MMBtu
-
05 2.2437: Recover waste heat from equipment $17,200 $15,000 - - $17,200
-
MMBtu
-
06 2.7135: Install occupancy sensors $12,520 $18,060 $12,520
245,029
kWh
- - -
07 2.8114: Change rate schedules or other changes in utility service $24,690 $109,600 - - - $24,690
08 2.7142: Utilize higher efficiency lamps and/or ballasts $4,305 $18,600 $2,721
48,600
kWh
$1,584
-
kW-mo/yr
- -
TOTAL RECOMMENDED $96,889 $165,190 $39,838
767,105
kWh
$12,246
-
kW-mo/yr
$20,115
-
MMBtu
$24,690
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs