| Assessment Year | 2010 |
|---|---|
| Principal Product | Needle Roller Bearings |
| NAICS | 332991: Ball and Roller Bearing Manufacturing |
| SIC | 3562: Ball and Roller Bearings |
| Sales Range | $50 M to 100M |
| # of Employees | 325 |
| Plant Area |
267,000
ft2
|
| Annual Production | 100,000,000
pieces
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $584,872 | 21,661,909 |
kWh
|
$0.027 |
| Electricity Demand | $636,225 | 42,415 |
kW-mo/yr
|
$15.00 |
| Electricity Fees | $39,237 | - |
|
- |
| Natural Gas | $378,618 | 67,440 |
MMBtu
|
$5.61 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $392,100 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7273: Install desiccant humidity control system | $392,100 | $250,000 |
$71,880
2,662,143
kWh
|
$61,720
-
kW-mo/yr
|
$258,500
-
MMBtu
|
|
| TOTAL RECOMMENDED | $392,100 | $250,000 |
$71,880
2,662,143
kWh
|
$61,720
-
kW-mo/yr
|
$258,500
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs