| Assessment Year | 2010 |
|---|---|
| Principal Product | Commercial carpet |
| NAICS | 314110: Carpet and Rug Mills |
| SIC | 2273: Carpets and Rugs |
| Sales Range | $50 M to 100M |
| # of Employees | 384 |
| Plant Area |
441,230
ft2
|
| Annual Production | 84,920,720
lb
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $369,138 | 8,768,000 |
kWh
|
$0.042 |
| Electricity Demand | $306,311 | 27,393 |
kW-mo/yr
|
$11.18 |
| Natural Gas | $345,701 | 55,749 |
MMBtu
|
$6.20 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $128,876 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $113,539 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,786 | $1,500 |
$4,966
170,820
kWh
|
$3,820
-
kW-mo/yr
|
- | - | |
| 02 | 3.2111: Install redundant equipment to avoid losses caused by equipment failure and routine maintenance | $307 | $50 |
$201
6,927
kWh
|
$106
-
kW-mo/yr
|
- | - | |
| 03 | 2.4322: Use or replace with energy efficient substitutes | $4,989 | $10,500 |
$2,820
97,020
kWh
|
$2,169
-
kW-mo/yr
|
- | - | |
| 04 | 2.2135: Repair and eliminate steam leaks | $1,027 | $300 | - | - |
$1,027
-
MMBtu
|
- | |
| 05 | 2.2211: Use optimum temperature | $103,726 | $187,530 | - | - |
$103,726
-
MMBtu
|
- | |
| 06 | 3.4111: Use closed cycle process to minimize waste water production | $10,041 | $20,000 | - | - | - |
$10,041
-
Tgal
|
|
| TOTAL RECOMMENDED | $128,876 | $219,880 |
$7,987
274,767
kWh
|
$6,095
-
kW-mo/yr
|
$104,753
-
MMBtu
|
$10,041
-
Tgal
|
||
| TOTAL IMPLEMENTED | $113,539 | $189,330 |
$4,966
170,820
kWh
|
$3,820
-
kW-mo/yr
|
$104,753
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs