Assessment Year | 2009 |
---|---|
Principal Product | Resilient Flooring |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3996: Linoleum, Asphalted-Felt-Base, and Other Hard Surface Floor Coverings, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 62 |
Plant Area |
73,000
ft2
|
Annual Production | 19,000
thousand feet
|
Production Hrs. Annual | 5,952
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $183,892 | 3,536,390 |
kWh
|
$0.052 |
Electricity Demand | $77,738 | 9,112 |
kW-mo/yr
|
$8.53 |
Natural Gas | $286,342 | 18,715 |
MMBtu
|
$15.30 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $52,392 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $20,185 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.2135: Repair and eliminate steam leaks | $7,130 | $2,100 | - | - |
$7,130
-
MMBtu
|
|
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $352 | - |
$254
4,880
kWh
|
$98
-
kW-mo/yr
|
- | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,117 | $890 |
$743
14,298
kWh
|
$374
-
kW-mo/yr
|
- | |
04 | 2.4239: Eliminate or reduce compressed air usage | $5,201 | $900 |
$3,753
72,175
kWh
|
$1,448
-
kW-mo/yr
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,586 | $42,920 |
$8,356
160,700
kWh
|
$3,230
-
kW-mo/yr
|
- | |
06 | 2.2414: Use waste heat from hot flue gases to preheat | $23,715 | $17,250 | - | - |
$23,715
-
MMBtu
|
|
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,291 | $4,515 |
$2,059
39,600
kWh
|
$1,232
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $52,392 | $68,575 |
$15,165
291,653
kWh
|
$6,382
-
kW-mo/yr
|
$30,845
-
MMBtu
|
||
TOTAL IMPLEMENTED | $20,185 | $45,910 |
$9,353
179,878
kWh
|
$3,702
-
kW-mo/yr
|
$7,130
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs