Assessment Year | 2009 |
---|---|
Principal Product | Yarn |
NAICS | 313110: Fiber, Yarn, and Thread Mills |
SIC | 2282: Yarn Texturizing, Throwing, Twisting, and Winding Mills |
Sales Range | $10 M to 50M |
# of Employees | 128 |
Plant Area |
600,000
ft2
|
Annual Production | 12,300,000
lb
|
Production Hrs. Annual | 7,400
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $508,134 | 8,536,662 |
kWh
|
$0.060 |
Electricity Demand | $160,980 | 18,543 |
kW-mo/yr
|
$8.68 |
Natural Gas | $652,994 | 64,035 |
MMBtu
|
$10.20 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $105,445 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $42,178 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $52,318 | $89,971 |
$43,128
677,047
kWh
|
$9,190
-
kW-mo/yr
|
- | |
02 | 2.7132: Install timers on light switches in little used areas | $8,794 | $4,000 |
$8,794
126,000
kWh
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $17,426 | $3,250 |
$17,426
249,660
kWh
|
- | - | |
04 | 2.4239: Eliminate or reduce compressed air usage | $14,518 | $6,000 |
$14,518
208,000
kWh
|
- | - | |
05 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $10,949 | - | - | - | $10,949 | |
06 | 2.4314: Use synthetic lubricant | $1,440 | - |
$1,440
20,663
kWh
|
- | - | |
TOTAL RECOMMENDED | $105,445 | $103,221 |
$85,306
1,281,370
kWh
|
$9,190
-
kW-mo/yr
|
$10,949 | ||
TOTAL IMPLEMENTED | $42,178 | $13,250 |
$42,178
604,323
kWh
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs