ITAC Assessment: GT0867
ITAC logo
ITAC Assessment: GT0867
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product Yarn
NAICS 313110: Fiber, Yarn, and Thread Mills
SIC 2282: Yarn Texturizing, Throwing, Twisting, and Winding Mills
Sales Range $10
M
to 50
M
# of Employees 128
Plant Area 600,000
ft2
Annual Production 12,300,000
lb
Production Hrs. Annual 7,400
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $508,134 8,536,662
kWh
Electricity Demand $160,980 18,543
kW-mo/yr
Natural Gas $652,994 64,035
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $105,445 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $42,178

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $52,318 $89,971 $43,128
677,047
kWh
$9,190
-
kW-mo/yr
-
02 2.7132: Install timers on light switches in little used areas $8,794 $4,000 $8,794
126,000
kWh
- -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $17,426 $3,250 $17,426
249,660
kWh
- -
04 2.4239: Eliminate or reduce compressed air usage $14,518 $6,000 $14,518
208,000
kWh
- -
05 2.3131: Reschedule plant operations or reduce load to avoid peaks $10,949 - - - $10,949
06 2.4314: Use synthetic lubricant $1,440 - $1,440
20,663
kWh
- -
TOTAL RECOMMENDED $105,445 $103,221 $85,306
1,281,370
kWh
$9,190
-
kW-mo/yr
$10,949
TOTAL IMPLEMENTED $42,178 $13,250 $42,178
604,323
kWh
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs