| Assessment Year | 2009 |
|---|---|
| Principal Product | Highway Coaches |
| NAICS | 336211: Motor Vehicle Body Manufacturing |
| SIC | 3713: Truck and Bus Bodies |
| Sales Range | $10 M to 50M |
| # of Employees | 200 |
| Plant Area |
212,000
ft2
|
| Annual Production | 60
pieces
|
| Production Hrs. Annual | 3,250
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $79,923 | 2,131,280 |
kWh
|
$0.038 |
| Electricity Demand | $129,130 | 8,259 |
kW-mo/yr
|
$15.64 |
| Natural Gas | $14,925 | 1,054 |
MMBtu
|
$14.16 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $18,516 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,845 | $17,464 |
$6,601
418
kWh
|
$4,244
-
kW-mo/yr
|
|
| 02 | 2.4239: Eliminate or reduce compressed air usage | $962 | - |
$962
25,660
kWh
|
- | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $439 | - |
$439
11,700
kWh
|
- | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $810 | $500 |
$317
8,450
kWh
|
$493
-
kW-mo/yr
|
|
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $325 | $449 |
$42
1,119
kWh
|
$283
-
kW-mo/yr
|
|
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,517 | $9,840 |
$1,377
36,725
kWh
|
$2,140
-
kW-mo/yr
|
|
| 07 | 2.4133: Use most efficient type of electric motors | $1,618 | $11,925 |
$348
9,262
kWh
|
$1,270
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $18,516 | $40,178 |
$10,086
93,334
kWh
|
$8,430
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs