Assessment Year | 2008 |
---|---|
Principal Product | Kraft Paper |
NAICS | 322130: Paperboard Mills |
SIC | 2631: Paperboard Mills |
Sales Range | $100 M to 500M |
# of Employees | 273 |
Plant Area |
3,000,000
ft2
|
Annual Production | 315,000
ton
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $4,084,356 | 110,983,405 |
kWh
|
$0.037 |
Natural Gas | $4,490,760 | 6,195,838 |
MMBtu
|
$0.72 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $887,973 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $292,310 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Wood Savings | Other Energy Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1331: Burn a less expensive grade of fuel | $98,980 | - | - | - |
$98,980
-
MMBtu
|
- | |
02 | 3.6123: Burn wood by-products for heat | $175,600 | $100,000 | - |
$175,600
-
MMBtu
|
- | - | |
03 | 2.1241: Reduce excessive boiler blowdown | $57,260 | - |
$3,256
59,200
kWh
|
- |
$34,466
-
MMBtu
|
$19,538
-
Tgal
|
|
04 | 2.2121: Increase amount of condensate returned | $292,310 | $18,200 |
$15,220
276,700
kWh
|
- |
$185,770
-
MMBtu
|
$91,320
-
Tgal
|
|
05 | 2.2136: Install / repair insulation on steam lines | $35,083 | $40,800 | - | - |
$35,083
-
MMBtu
|
- | |
06 | 2.3412: Use waste heat to produce steam to drive a steam turbine-generator | $228,740 | $900,000 |
$1,070,900
19,471,200
kWh
|
- |
$(-842,160.0)
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $887,973 | $1,059,000 |
$1,089,376
19,807,100
kWh
|
$175,600
-
MMBtu
|
$(-487,861.0)
-
MMBtu
|
$110,858
-
Tgal
|
||
TOTAL IMPLEMENTED | $292,310 | $18,200 |
$15,220
276,700
kWh
|
- |
$185,770
-
MMBtu
|
$91,320
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Wood Savings | Other Energy Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs