ITAC Assessment: GT0849
ITAC logo
ITAC Assessment: GT0849
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Kraft Paper
NAICS 322130: Paperboard Mills
SIC 2631: Paperboard Mills
Sales Range $100
M
to 500
M
# of Employees 273
Plant Area 3,000,000
ft2
Annual Production 315,000
ton
Production Hrs. Annual 8,400
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $4,084,356 110,983,405
kWh
Natural Gas $4,490,760 6,195,838
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $887,973 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $292,310

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Wood Savings Other Energy Savings Water Consumption Savings
01 2.1331: Burn a less expensive grade of fuel $98,980 - - - $98,980
-
MMBtu
-
02 3.6123: Burn wood by-products for heat $175,600 $100,000 - $175,600
-
MMBtu
- -
03 2.1241: Reduce excessive boiler blowdown $57,260 - $3,256
59,200
kWh
- $34,466
-
MMBtu
$19,538
-
Tgal
04 2.2121: Increase amount of condensate returned $292,310 $18,200 $15,220
276,700
kWh
- $185,770
-
MMBtu
$91,320
-
Tgal
05 2.2136: Install / repair insulation on steam lines $35,083 $40,800 - - $35,083
-
MMBtu
-
06 2.3412: Use waste heat to produce steam to drive a steam turbine-generator $228,740 $900,000 $1,070,900
19,471,200
kWh
- $(-842,160.0)
-
MMBtu
-
TOTAL RECOMMENDED $887,973 $1,059,000 $1,089,376
19,807,100
kWh
$175,600
-
MMBtu
$(-487,861.0)
-
MMBtu
$110,858
-
Tgal
TOTAL IMPLEMENTED $292,310 $18,200 $15,220
276,700
kWh
- $185,770
-
MMBtu
$91,320
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Wood Savings Other Energy Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs