Assessment Year | 2007 |
---|---|
Principal Product | Sheet Metal Work |
NAICS | 332322: Sheet Metal Work Manufacturing |
SIC | 3444: Sheet Metal Work |
Sales Range | $10 M to 50M |
# of Employees | 137 |
Plant Area |
120,000
ft2
|
Annual Production | 1,000
units
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $132,086 | 3,083,394 |
kWh
|
$0.043 |
Electricity Demand | $54,373 | 7,618 |
kW-mo/yr
|
$7.14 |
Electricity Fees | $24,739 | - |
|
- |
Natural Gas | $326,822 | 25,591 |
MMBtu
|
$12.77 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $51,352 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $46,749 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,317 | $5,346 |
$1,191
32,350
kWh
|
$1,126
-
kW-mo/yr
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $22,858 | $49,525 |
$11,748
319,250
kWh
|
$11,110
-
kW-mo/yr
|
- | |
03 | 2.4234: Cool compressor air intake with heat exchanger | $4,603 | $5,050 |
$(-261.0)
(-4,408)
kWh
|
- |
$4,864
-
MMBtu
|
|
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $14,992 | $1,000 |
$14,992
252,824
kWh
|
- | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $6,582 | - |
$6,582
110,998
kWh
|
- | - | |
TOTAL RECOMMENDED | $51,352 | $60,921 |
$34,252
711,014
kWh
|
$12,236
-
kW-mo/yr
|
$4,864
-
MMBtu
|
||
TOTAL IMPLEMENTED | $46,749 | $55,871 |
$34,513
715,422
kWh
|
$12,236
-
kW-mo/yr
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs