Assessment Year | 2007 |
---|---|
Principal Product | Printed Carpet |
NAICS | 314110: Carpet and Rug Mills |
SIC | 2273: Carpets and Rugs |
Sales Range | $50 M to 100M |
# of Employees | 85 |
Plant Area |
110,000
ft2
|
Annual Production | 14,000,000
lb
|
Production Hrs. Annual | 3,600
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $148,215 | 3,487,400 |
kWh
|
$0.043 |
Electricity Demand | $96,031 | 10,718 |
kW-mo/yr
|
$8.96 |
Electricity Fees | $39,763 | - |
|
- |
Natural Gas | $687,089 | 66,484 |
MMBtu
|
$10.33 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $100,133 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $54,921 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.5192: Modify textile dryers | $47,625 | $36,000 | - | - |
$47,625
-
MMBtu
|
- | |
02 | 2.2314: Replace heat treating oven with more efficient unit | $24,860 | $28,000 | - | - |
$24,860
-
MMBtu
|
- | |
03 | 2.1224: Replace boiler | $14,853 | $18,000 | - | - |
$12,613
-
MMBtu
|
$2,240 | |
04 | 2.2163: Use minimum steam operating pressure | $1,405 | - | - | - |
$1,405
-
MMBtu
|
- | |
05 | 2.2136: Install / repair insulation on steam lines | $1,013 | $2,000 | - | - |
$1,013
-
MMBtu
|
- | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,074 | $1,074 |
$631
14,840
kWh
|
$443
-
kW-mo/yr
|
- | - | |
07 | 2.8114: Change rate schedules or other changes in utility service | $4,094 | $8,200 | - | - | - | $4,094 | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,448 | $5,454 |
$925
21,773
kWh
|
$523
-
kW-mo/yr
|
- | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,690 | $6,290 |
$1,299
30,561
kWh
|
$391
-
kW-mo/yr
|
- | - | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,071 | $11,479 |
$1,324
31,145
kWh
|
$747
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $100,133 | $116,497 |
$4,179
98,319
kWh
|
$2,104
-
kW-mo/yr
|
$87,516
-
MMBtu
|
$6,334 | ||
TOTAL IMPLEMENTED | $54,921 | $62,297 |
$4,179
98,319
kWh
|
$2,104
-
kW-mo/yr
|
$48,638
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs