ITAC Assessment: GT0829
ITAC logo
ITAC Assessment: GT0829
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Fuel Pumps
NAICS 336310: Motor Vehicle Gasoline Engine and Engine Parts Manufacturing
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $100
M
to 500
M
# of Employees 357
Plant Area 164,000
ft2
Annual Production 6,000,000
pieces
Production Hrs. Annual 7,500
hrs
Location (State) South Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $386,416 10,182,266
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $55,994 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,481

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,481 $500 $1,481
39,076
kWh
02 2.4239: Eliminate or reduce compressed air usage $45,543 $32,500 $45,543
1,201,671
kWh
03 2.4133: Use most efficient type of electric motors $3,510 $11,358 $3,510
92,603
kWh
04 2.7142: Utilize higher efficiency lamps and/or ballasts $5,460 $13,714 $5,460
144,069
kWh
TOTAL RECOMMENDED $55,994 $58,072 $55,994
1,477,419
kWh
TOTAL IMPLEMENTED $1,481 $500 $1,481
39,076
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs