Assessment Year | 2006 |
---|---|
Principal Product | Chicken |
NAICS | 311615: Poultry Processing |
SIC | 2015: Poultry Slaughtering and Processing |
Sales Range | greater than $500 M |
# of Employees | 4,600 |
Plant Area |
500,000
ft2
|
Annual Production | 700,000,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,886,786 | 31,284,464 |
kWh
|
$0.060 |
Natural Gas | $3,362,812 | 334,418 |
MMBtu
|
$10.06 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $685,319 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $255,200 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $5,551 | $1,487 |
$5,551
109,489
kWh
|
- | - | - | |
02 | 2.2414: Use waste heat from hot flue gases to preheat | $325,944 | $38,000 | - |
$325,944
-
MMBtu
|
- | - | |
03 | 2.2128: Use steam condensate for hot water supply (non-potable) | $85,490 | $12,500 | - |
$85,490
-
MMBtu
|
- | - | |
04 | 2.2162: Reduce excess steam bleeding | $10,400 | $39,900 | - |
$9,909
-
MMBtu
|
- |
$491
-
Tgal
|
|
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,421 | $4,053 |
$2,421
47,750
kWh
|
- | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,361 | $2,328 |
$2,361
46,560
kWh
|
- | - | - | |
07 | 2.6242: Minimize operation of equipment maintained in standby condition | $2,734 | $3,500 |
$963
19,000
kWh
|
$1,771
-
MMBtu
|
- | - | |
08 | 3.4155: Meter waste water | $81,583 | $5,250 | - | - | $81,583 | - | |
09 | 2.2437: Recover waste heat from equipment | $158,948 | $150,000 | - |
$158,948
-
MMBtu
|
- | - | |
10 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,887 | $3,400 |
$9,887
195,000
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $685,319 | $260,418 |
$21,183
417,799
kWh
|
$582,062
-
MMBtu
|
$81,583 |
$491
-
Tgal
|
||
TOTAL IMPLEMENTED | $255,200 | $165,031 |
$14,669
289,310
kWh
|
$158,948
-
MMBtu
|
$81,583 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs