ITAC Assessment: GT0824
ITAC logo
ITAC Assessment: GT0824
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Nylon Carpet Yarn
NAICS 313110: Fiber, Yarn, and Thread Mills
SIC 2281: Yarn Spinning Mills
Sales Range $50
M
to 100
M
# of Employees 170
Plant Area 105,000
ft2
Annual Production 30,000,000
lb
Production Hrs. Annual 6,600
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,166,580 20,862,201
kWh
Electricity Demand $3,960 34,009
kW-mo/yr
Natural Gas $375,329 34,109
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $62,140 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $36,486

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $5,310 $6,700 $5,310
100,947
kWh
- -
02 2.4239: Eliminate or reduce compressed air usage $2,327 $1,600 $2,327
44,240
kWh
- -
03 2.4226: Use / purchase optimum sized compressor $4,767 $9,900 $4,767
90,625
kWh
- -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $20,205 $1,450 $20,205
384,120
kWh
- -
05 3.4116: Meter recycled water (to reduce sewer charges) $4,702 $600 - - $4,702
06 2.6218: Turn off equipment when not in use $16,185 $1,320 $547
1,118
kWh
$15,638
-
MMBtu
-
07 2.4239: Eliminate or reduce compressed air usage $8,644 - $8,644
164,340
kWh
- -
TOTAL RECOMMENDED $62,140 $21,570 $41,800
785,390
kWh
$15,638
-
MMBtu
$4,702
TOTAL IMPLEMENTED $36,486 $9,750 $36,486
693,647
kWh
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs