Assessment Year | 2006 |
---|---|
Principal Product | Nylon Carpet Yarn |
NAICS | 313110: Fiber, Yarn, and Thread Mills |
SIC | 2281: Yarn Spinning Mills |
Sales Range | $50 M to 100M |
# of Employees | 170 |
Plant Area |
105,000
ft2
|
Annual Production | 30,000,000
lb
|
Production Hrs. Annual | 6,600
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,166,580 | 20,862,201 |
kWh
|
$0.056 |
Electricity Demand | $3,960 | 34,009 |
kW-mo/yr
|
$0.12 |
Natural Gas | $375,329 | 34,109 |
MMBtu
|
$11.00 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $62,140 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $36,486 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,310 | $6,700 |
$5,310
100,947
kWh
|
- | - | |
02 | 2.4239: Eliminate or reduce compressed air usage | $2,327 | $1,600 |
$2,327
44,240
kWh
|
- | - | |
03 | 2.4226: Use / purchase optimum sized compressor | $4,767 | $9,900 |
$4,767
90,625
kWh
|
- | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $20,205 | $1,450 |
$20,205
384,120
kWh
|
- | - | |
05 | 3.4116: Meter recycled water (to reduce sewer charges) | $4,702 | $600 | - | - | $4,702 | |
06 | 2.6218: Turn off equipment when not in use | $16,185 | $1,320 |
$547
1,118
kWh
|
$15,638
-
MMBtu
|
- | |
07 | 2.4239: Eliminate or reduce compressed air usage | $8,644 | - |
$8,644
164,340
kWh
|
- | - | |
TOTAL RECOMMENDED | $62,140 | $21,570 |
$41,800
785,390
kWh
|
$15,638
-
MMBtu
|
$4,702 | ||
TOTAL IMPLEMENTED | $36,486 | $9,750 |
$36,486
693,647
kWh
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs