Assessment Year | 2005 |
---|---|
Principal Product | Rubber Tread |
NAICS | 326211: Tire Manufacturing (except Retreading) |
SIC | 3011: Tires and Inner Tubes |
Sales Range | $100 M to 500M |
# of Employees | 135 |
Plant Area |
475,000
ft2
|
Annual Production | 57,000,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $655,289 | 17,689,343 |
kWh
|
$0.037 |
Electricity Demand | $327,644 | 48,700 |
kW-mo/yr
|
$6.73 |
Electricity Fees | $73,984 | - |
|
- |
Natural Gas | $428,797 | 48,795 |
MMBtu
|
$8.79 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $82,993 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $62,760 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $5,381 | - | - |
$5,381
-
kW-mo/yr
|
- | |
02 | 2.2414: Use waste heat from hot flue gases to preheat | $7,360 | $8,000 | - | - |
$7,360
-
MMBtu
|
|
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,172 | $565 |
$1,554
39,752
kWh
|
$618
-
kW-mo/yr
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $18,158 | $41,528 |
$14,511
371,129
kWh
|
$3,647
-
kW-mo/yr
|
- | |
05 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $4,836 | - |
$3,252
83,160
kWh
|
$1,584
-
kW-mo/yr
|
- | |
06 | 2.4314: Use synthetic lubricant | $22,247 | - |
$16,674
426,437
kWh
|
$5,573
-
kW-mo/yr
|
- | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $16,974 | $1,250 |
$12,166
311,144
kWh
|
$4,808
-
kW-mo/yr
|
- | |
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,865 | $3,500 |
$4,216
107,815
kWh
|
$1,649
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $82,993 | $54,843 |
$52,373
1,339,437
kWh
|
$23,260
-
kW-mo/yr
|
$7,360
-
MMBtu
|
||
TOTAL IMPLEMENTED | $62,760 | $42,778 |
$43,351
1,108,710
kWh
|
$19,409
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs