Assessment Year | 2019 |
---|---|
Principal Product | roofing shingles, asphalt products |
NAICS | 324122: Asphalt Shingle and Coating Materials Manufacturing |
SIC | 2952: Asphalt Felts and Coatings |
Sales Range | $50 M to 100M |
# of Employees | 216 |
Plant Area |
233,000
ft2
|
Annual Production | 220,000,000
ton
|
Production Hrs. Annual | 6,624
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $581,692 | 18,384,836 |
kWh
|
$0.032 | |
Electricity Demand | $336,613 | 37,819 |
kW-mo/yr
|
$8.90 | |
Electricity Fees | $30,710 | - |
|
- | |
Natural Gas | $888,279 | 264,697 |
MMBtu
|
$3.36 | |
Waste Disposal Costs | |||||
Solid Waste (non-haz) | $133,950 | 1,140,000 |
lb
|
$0.12 | |
TOTAL YEARLY COSTS | $1,971,244 | ||||
RECOMMENDED SAVINGS* | $630,559 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.8121: Apply for tax-free status for energy purchases | $200,328 | $100 | - | - | $200,328 | - | |
02 | 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $180,556 | $1,134,251 |
$180,556
6,613,800
kWh
|
- | - | - | |
03 | 2.2522: Isolate hot or cold equipment | $133,950 | $353,500 | - | - | - |
$133,950
-
lb
|
|
04 | 2.9114: Use solar heat to make electricty | $48,197 | $757,373 |
$48,197
1,292,134
kWh
|
- | - | - | |
05 | 2.3212: Optimize plant power factor | $41,452 | $72,710 | - |
$41,452
-
kW-mo/yr
|
- | - | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $14,150 | $36,000 |
$10,220
270,084
kWh
|
$3,930
-
kW-mo/yr
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,577 | $17,085 |
$6,932
185,855
kWh
|
$2,645
-
kW-mo/yr
|
- | - | |
08 | 2.4314: Use synthetic lubricant | $2,349 | $1,600 |
$1,328
35,592
kWh
|
$1,021
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $630,559 | $2,372,619 |
$247,233
8,397,465
kWh
|
$49,048
-
kW-mo/yr
|
$200,328 |
$133,950
-
lb
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs