| Assessment Year | 2005 |
|---|---|
| Principal Product | Turbine Blades |
| NAICS | 336412: Aircraft Engine and Engine Parts Manufacturing |
| SIC | 3724: Aircraft Engines and Engine Parts |
| Sales Range | $50 M to 100M |
| # of Employees | 328 |
| Plant Area |
235,000
ft2
|
| Annual Production | 200,000
pieces
|
| Production Hrs. Annual | 7,488
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,175,768 | 24,799,764 |
kWh
|
$0.047 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $128,330 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,230 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
|---|---|---|---|---|---|
| 01 | 2.2511: Insulate bare equipment | $22,100 | $2,782 |
$22,100
476,508
kWh
|
|
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,230 | $2,150 |
$1,230
26,422
kWh
|
|
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $24,900 | $52,200 |
$24,900
536,260
kWh
|
|
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,300 | $23,431 |
$13,300
285,650
kWh
|
|
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,600 | $2,613 |
$1,600
34,499
kWh
|
|
| 06 | 2.4133: Use most efficient type of electric motors | $28,900 | $135,800 |
$28,900
622,458
kWh
|
|
| 07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $26,000 | $59,670 |
$26,000
560,000
kWh
|
|
| 08 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $10,300 | $13,870 |
$10,300
222,250
kWh
|
|
| TOTAL RECOMMENDED | $128,330 | $292,516 |
$128,330
2,764,047
kWh
|
||
| TOTAL IMPLEMENTED | $1,230 | $2,150 |
$1,230
26,422
kWh
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs